The Network of
drinking water, fire and sanitation
Residential
assembly Algushi -Misurata
|
Project
name
|
21/2001
|
Contract
No
|
441,368.600. LD
|
Value
|
The executive
organ of metal constructions and industrial housing
|
Contractor
|
Rain water
drainage network
Residential
assembly Algushi -Misurata
|
Project
name
|
22/2001
|
Contract
No
|
307,777.280.LD
|
Value
|
The executive
organ of metal constructions and industrial housing
|
Contractor
|
The sewerage
network linking on the main pumping station
|
Project
name
|
addendum contract
21/2001
|
Contract
No
|
77,638.800.LD
|
Value
|
The executive
organ of development and industrial investment
|
Contractor
|
Linking the rain
water drainage to the main pumping station
|
Project
name
|
addendum contract
22/2001
|
Contract
No
|
79952.250 LD
|
Value
|
The executive
organ of development and industrial investment
|
Contractor
|
Implementation of
Alshubiha road
|
Project
name
|
34/2001
|
Contract
No
|
494,357 LD
|
Value
|
People's
Committee for transport and communications of almrgeb
|
Contractor
|
Implementation of
the soil works for the track of the rail way / Alhisha
Aljadida - Sirte
|
Project
name
|
183/2001
|
Contract
No
|
451,791.895.LD
|
Value
|
The executive
organ of the railway
|
Contractor
|
Implementation of
(6) stations for voltage reduce
Site: Residential
assembly Algushi -Misurata
|
Project
name
|
02/2002
|
Contract
No
|
495,840.000.LD
|
Value
|
The executive
organ of metal constructions and industrial housing
|
Contractor
|
Implementation of
the soil bridge for railway line in the Aldafniah - Misurata
|
Project
name
|
141/69
|
Contract
No
|
497,917 LD
|
Value
|
The executive
organ of the railway
|
Contractor
|
The civil works
for the structure of the machinery factory for cut and clear
marble
Qasser Ahmad
|
Project
name
|
Agreement
|
Contract
No
|
34,348.230 LD
|
Value
|
The executive
organ of metal constructions and industrial housing
|
Contractor
|
filling wells
located within the contract 141-69
|
Project
name
|
assign
No:4.4-751-70
|
Contract
No
|
4,900 LD
|
Value
|
The executive
organ of the road for the iron branch others
|
Contractor
|
Maintenance works
of temporary conductivity for Alwafa plant project.
|
Project
name
|
001-3233-c-2465
|
Contract
No
|
|
Value
|
GTS Co. for
contracts Ltd.
|
Contractor
|
The works of west
of Libya's gas project, desert field of Alwafa
|
Project
name
|
Agreement
|
Contract
No
|
|
Value
|
Deawoo Company
for Engineering and Construction Ltd. – Korea
|
Contractor
|
Implementation of
concrete structures for (24) housing units model (e)
|
Project
name
|
166/2005
|
Contract
No
|
485,526.370 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Cleaning of the
third round road course/Tripoli
|
Project
name
|
3/2006
|
Contract
No
|
390,000 LD
|
Value
|
Project
implementation 25000 housing units
|
Contractor
|
Implementation of
concrete structures for (8) housing units model (e)
|
Project
name
|
62/2006
|
Contract
No
|
161,619.909 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Maintenance of
the road (Daraj - alwafa field)
|
Project
name
|
C10371/WA/05
|
Contract
No
|
161,619.909 LD
|
Value
|
ENI Gas NBA – Libya branch
|
Contractor
|
Finalizing of 18
housing units in Aljazeera - Misurata
|
Project
name
|
164/2005
|
Contract
No
|
401,729.760 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Cleaning and
implementation the sides of heavy transport road - Misurata
|
Project
name
|
01/2006
|
Contract
No
|
472,250.000 LD
|
Value
|
People's
Committee for Housing and Utilities and the Environment,
Misurata
|
Contractor
|
Implementation of
the finishing works for 16 housing units - Sirt
|
Project
name
|
178/2006
|
Contract
No
|
459,802.776 LD
|
Value
|
Project of
implementation 25000 housing
|
Contractor
|
Implementation of
100 housing units, in Zamzam - Sirte
|
Project
name
|
85/2006
|
Contract
No
|
5,636,632.680 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Implementation of
the first phase of filling Almlaita's salt swamp - Misurata
|
Project
name
|
333/2006
|
Contract
No
|
480,000.000 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
The
implementation of infrastructure networks in the residential
assembly Qasser ahmed
|
Project
name
|
105/2007
|
Contract
No
|
2,277,000.000 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
implementation of
the Civil works for the ceramic tiles factory in Alkrarim
|
Project
name
|
Agreement
|
Contract
No
|
405,0913.730 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
Implementation of
metal sheets structures for the production halls of the
factory of ceramic tiles
|
Project
name
|
Agreement
|
Contract
No
|
482,250.000 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
Implementation of
3 power stations 11KVA in the ceramic tiles factory
|
Project
name
|
Agreement
|
Contract
No
|
269,873.250 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
Implementation of
ceramic tiles factory's fence and gates and guard's room
|
Project
name
|
Agreement
|
Contract
No
|
239,226.000 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
Implementation of
ceramic tiles factory's Laboratory
|
Project
name
|
Agreement
|
Contract
No
|
442,576.000 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
The
implementation of water reservoir of the ceramic tiles
factory
|
Project
name
|
Agreement
|
Contract
No
|
70,588.000 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
The
implementation of the track of the gas pipeline for the
ceramic tiles factory
|
Project
name
|
Agreement
|
Contract
No
|
217,412.000 LD
|
Value
|
Libyan Tunisian
company for building materials industry
|
Contractor
|
Implementation of
the second phase of filling Almlaita's salt swamp - Misurata
|
Project
name
|
404/2007
|
Contract
No
|
480,000.000 LD
|
Value
|
Project
implementation 25000 housing units
|
Contractor
|
Implementation of
external and fencing works for 24 housing units model E
|
Project
name
|
403/2007
|
Contract
No
|
397,958.069 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Implementation of
external and fencing works for 26 housing units model E
|
Project
name
|
366/2007
|
Contract
No
|
430,916.650 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Implementation of
external and fencing works for 24 housing units model E
|
Project
name
|
397/2007
|
Contract
No
|
377,958.069 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
Implementation of
the third phase of filling Almlaita's salt swamp - Misurata
|
Project
name
|
543/2006
|
Contract
No
|
480,000.000 LD
|
Value
|
Project
implementation 25000 housing units
|
Contractor
|
Implementation of
external and fencing works for 26 housing units model E
|
Project
name
|
352/2007
|
Contract
No
|
377,958.069 LD
|
Value
|
Project of
implementation 25000 housing units
|
Contractor
|
The implementation of the leveling and cleaning of the slag
throwing area in the iron and steel company
|
Project
name
|
26/2007
|
Contract
No
|
842,400.000 LD
|
Value
|
Libyan Iron and Steel Company
|
Contractor
|
Implementation of parking Place in the Medical Technology
Faculty of and the road linking between the site and the
coastal road.
|
Project name
|
41/2009
|
Contract No
|
1,425,675.000 LD
|
Value
|
Organization for Development of Administrative Centers
(O.D.A.C.)
|
Contractor
|
|